paper mill

Client

Location: paper mill
Velsen-Noord, the Netherlands
Duration: 2 weeks
Project management: IR

Equipment
  • Electrically driven centrifugal oil-free air compressor 70 m³ / min
  • Transformer from 6000 volts to 400 volts
  • Air tank 10,000 liters
  • Pressure regulators
  • Cooling water machine 400 kW

Testimonials

On a Friday evening we called the emergency number of the RTC Group and immediately the phone was picked up.

Maintenance manager steel

factory Belgium

With tremendous fast response time they helped us to get our compressed air production to an acceptable level.

Project leader

The Netherlands

This solution has saved us huge amounts of diesel, pollution and not the least euros.

Senior buyer

Germany